Enabling works for construction
Enabling works is a generic description for site preparation works that might take place prior to work under the main construction contract.
This could include:
- Demolition.
- Site clearance.
- Tree protection.
- Diversion and/or disconnection of existing site services.
- Geotechnical and exploratory ground investigation.
- Decoupling from existing buildings.
- Decontamination.
- Ground improvement and/or compaction.
- Excavation of known below-ground obstructions.
- Survey work.
- Creation of access routes.
- Perimeter fencing and security provisions.
- Work to neighbouring buildings.
- Discharging planning conditions that must be satisfied prior to construction commencing.
- Historical architectural investigation fieldwork.
- Access ramps.
- Signage provisions.
- Provision of statutory utilities to the site.
Enabling works might be preceded by 'mobilisation' activities, carried out after the client has selected the contractor, but before works commence on site. These are preparatory activities, such as; preparing method statements, arranging road closures, placing necessary sub-contracts, and so on. See Mobilisation for more information.
NB: NRM1: Order of cost estimating and cost planning for capital building work, defines enabling works as:
'...works executed ahead of the main building contract. Enabling works are employer and/or project team specified works, which might include a mixture of facilitating works and new building works (e.g. site preparatory works such as major demolition, removal of contaminated materials, reptile mitigation measures, and soil stabilisation; together with new sewers, new access road, new drainage, new retaining walls, and minor new building works).'
This is as opposed to facilitating works, which NRM1 defines as:
‘…all components measured and incorporated in group element 0 (i.e. Facilitating works). Includes specialist works which, normally, need to be completed before any building works can commence (e.g. major demolition works, soil stabilisation works and or temporary diversion of mains drainage).’
Advantages of having an enabling works contract:
- On site sooner.
- Can saves time and money.
- Could have a specialist contractor for carrying out that particular type of works eg. demolition.
Disadvantages:
- The cost and time to make up two separate contracts
- Process complexity involved in making up two separate contracts
- If there are two different contractors; liability and hand-over issues.
[edit] Related articles on Designing Buildings
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.